Calculator
Progressive Payment Calculator
Cash and loan disbursement schedule across BUC condo construction milestones.
Some details are filled in from your earlier calculations in this tab.
Your inputs
Summary
Monthly repayment on the full loan (after CSC)
S$0
- Total cash + CPF outlay
- S$0
- Total loan disbursed
- S$0
- Buyer's Stamp Duty (BSD)
- S$0
- ABSD
- S$0
Got questions? Discuss this further with David.
Your figures go into the message so David sees the full picture. You can edit it before sending.
Disbursement schedule by milestone
| Order of Payment | Progress of Payment | Percentage of Payment |
|---|
Your own cash and CPF are paid first: 20% by the S&P, and any balance of your down payment at the next stages. The bank disburses only after that, and charges interest only on the cumulative amount disbursed, so monthly servicing ramps up as construction progresses.
- Results are indicative only and not a bank-approved quotation, IRAS assessment, or HDB confirmation.
- Interest rates, stamp-duty rates, LTV limits and CPF rules change. Verify the latest with MAS, IRAS, HDB and your lender before transacting.
- Consult a qualified mortgage broker, conveyancing lawyer, or accountant for advice specific to your situation.
- BuyNewCondo.sg accepts no liability for decisions made on the basis of these calculations.
References
Last updated: 25 Sep 2026
Frequently Asked Questions
The standard sale agreement in the Housing Developers Rules (Form 5) sets the schedule: 5% booking, 15% on S&P signing (or 20% total with the booking), then 10% foundation, 10% reinforced concrete framework, 5% partition walls, 5% roofing, 5% door and window frames/wiring/plumbing/plastering, 5% car park/drains/roads, 25% at TOP (Temporary Occupation Permit), and the final 15%, which Form 5 sets out in parts across the Completion Date, the CSC (Certificate of Statutory Completion) and the Final Payment Date.
The bank only charges interest on the cumulative amount it has disbursed to the developer. At the foundation stage, that is only a small share of your loan. The last disbursement is the final 15%, around CSC; from then on you pay the full monthly repayment shown here.
Sub-sale of an uncompleted unit is allowed but you'll pay Seller's Stamp Duty (SSD) if within the SSD Period. Check with your lawyer to confirm how much SSD is applicable.
No. This calculator assumes the standard progressive payment schedule above. A deferred payment scheme follows a different schedule, so check the one in your own option and sale agreement.